
Liquidated Damages and Extensions of Time
Beschreibung
Alles über E-Books | Antworten auf Fragen rund um E-Books, Kopierschutz und Dateiformate finden Sie in unserem Info- & Hilfebereich.
Rezensionen / Stimmen
"Practitioners of construction contracts owe a debt to BrianEggleston for this updated publication and the sooner they add thisto their library the better." (The Expert and DisputeResolver, Spring 2009) "Eggleston has once again hit the nail on the head with thishigh-quality, easy to understand legal textbook written for lawyersand the industry." (Building Magazine, February 2009)Weitere Details
Weitere Ausgaben
Person
Inhalt
- Intro
- Contents
- Preface to Third Edition
- References
- Acknowledgements
- Chapter 1: Introduction
- 1.1 General overview
- 1.2 Legal developments
- 1.3 Contractual developments
- Chapter 2: Time in contracts
- 2.1 Problems with terminology
- 2.2 Conditions and warranties
- 2.3 Termination
- 2.4 Time for performance
- 2.5 Time of the essence
- 2.6 Notice making time of the essence
- 2.7 Time at large
- 2.8 Reasonable time
- 2.9 Fixing time by reference to correspondence
- 2.10 The effect of time at large on the contract price
- Chapter 3: Damages for late completion
- 3.1 Liquidated and general damages distinguished
- 3.2 Principles of general damages
- 3.3 Alternative remedies
- 3.4 Can general damages exceed liquidated damages?
- 3.5 Under-liquidation of damages
- 3.6 Double damages
- 3.7 Liability for damages in tort
- 3.8 The Panatown problem
- Chapter 4: Liquidated damages and penalties
- 4.1 Penalties-general introduction
- 4.2 Liquidated damages
- 4.3 Liquidated damages and penalties distinguished
- 4.4 Pre-estimates of damage
- 4.5 Particular aspects of penalty clauses
- 4.6 Evidential matters
- 4.7 Bonus clauses
- 4.8 Site occupation charges
- Chapter 5: Prevention
- 5.1 Principle of prevention
- 5.2 Need for extension of time provisions
- 5.3 Defining an act of prevention
- 5.4 Prevention after the completion date
- 5.5 Effect of late variations on unliquidated damages
- 5.6 Prevention and time at large
- 5.7 Conditions precedent and time-bars
- 5.8 Steria Ltd v. Sigma Wireless Communications Ltd (2007)
- Chapter 6: Legal construction of liquidated damages clauses
- 6.1 Rules of construction
- 6.2 Contra proferentem rule
- 6.3 Restrictions on implied terms
- 6.4 'Catch all' phrases
- 6.5 Inconsistencies in drafting
- Chapter 7: Effects of determination
- 7.1 The question of continuing responsibility
- 7.2 British Glanzstoff
- 7.3 Contractual provisions
- 7.4 Novations
- 7.5 Summary on liquidated damages
- 7.6 Determination and limitation on liability
- Chapter 8: Problems with sectional completion
- 8.1 Discovering the parties' intentions
- 8.2 Proportioning down clauses
- 8.3 Provisions for sectional completion
- 8.4 Requirements not fully specified
- Chapter 9: Application to sub-contractors
- 9.1 Effect of 'stepping-down' provisions
- 9.2 Can there be a genuine pre-estimate of loss?
- 9.3 Commercial considerations
- 9.4 Nominated sub-contracts
- Chapter 10: Recovery of liquidated damages
- 10.1 When do liquidated damages become payable?
- 10.2 Meaning of completion
- 10.3 Certificates and conditions precedent
- 10.4 Methods of recovery
- 10.5 Time limits on recovery
- 10.6 Interest on repayment
- 10.7 Withholding notices
- 10.8 Decisions of adjudicators
- Chapter 11: Defences / challenges to liquidated damages
- 11.1 Benefits of precedents
- 11.2 Extension of time due
- 11.3 Completion achieved earlier than certified
- 11.4 Certificates not valid
- 11.5 Conditions precedent not observed
- 11.6 No date for commencement
- 11.7 Prevention
- 11.8 Penalties
- 11.9 Provisions void for uncertainty
- 11.10 Waiver / estoppel
- 11.11 Unfair Contract Terms Act 1977
- Chapter 12: Extensions of time
- 12.1 Purposes of extension provisions
- 12.2 Notices, applications and assessments
- 12.3 Time for granting extensions
- 12.4 Application to claims
- 12.5 Proof of entitlement
- 12.6 Global claims
- 12.7 The liability of certifiers
- Chapter 13: Relevant events
- 13.1 Force majeure
- 13.2 Adverse weather
- 13.3 Civil commotion, strikes, etc.
- 13.4 Damage to the works
- 13.5 Sub-contractors
- 13.6 Non-availability of resources
- 13.7 Statutory undertakers' works
- 13.8 Other special circumstances
- 13.9 Statutory powers
- 13.10 Possession and access
- 13.11 Late issue of drawings and instructions
- 13.12 Variations and extra works
- 13.13 Compliance with instructions
- 13.14 Unforeseen physical conditions
- Chapter 14: Causation and concurrency
- 14.1 Introduction
- 14.2 Causation generally
- 14.3 Concurrency generally
- 14.4 Dominant cause approach
- 14.5 Apportionment
- 14.6 Rules for extensions of time
- 14.7 Discussion on various approaches
- 14.8 Extensions when in culpable delay
- Chapter 15: Programmes, method statements and best endeavours
- 15.1 Status of contractor's programmes and method statements
- 15.2 Programmes
- 15.3 Shortened programmes
- 15.4 Method statements
- 15.5 Best endeavours and the like
- Chapter 16: Delay analysis
- 16.1 Introduction
- 16.2 Critical paths
- 16.3 Float
- 16.4 Methods of delay analysis
- 16.5 Judicial comments on delay analysis
- Chapter 17: Building forms
- 17.1 Introduction
- 17.2 JCT 2005 contracts
- 17.3 Commencement and completion
- 17.4 Notification of delay
- 17.5 Extension of time
- 17.6 Relevant events
- 17.7 Non-completion certificates
- 17.8 Payment of liquidated damages
- 17.9 Proportioning down of liquidated damages
- Chapter 18: Civil engineering forms
- 18.1 NEC 3-Engineering and Construction Contract, 2005
- 18.2 ICE Conditions of Contract-7th edition, 1999
- 18.3 ICE Conditions of Contract for Minor Works-3rd edition, 2001
- 18.4 CECA Form of sub-contract, 2008
- Chapter 19: Process and plant forms
- 19.1 The IChemE Red Book-4th edition, 2001
- 19.2 MF / 1 (Rev 4) 2000 edition
- Chapter 20: FIDIC conditions of contract 1999
- 20.1 FIDIC contracts
- 20.2 Commencement and completion
- 20.3 Extension of time
- 20.4 Delay damages
- Table of Cases
- Index
Systemvoraussetzungen
Dateiformat: PDF
Kopierschutz: Adobe-DRM (Digital Rights Management)
Systemvoraussetzungen:
- Computer (Windows; MacOS X; Linux): Installieren Sie bereits vor dem Download die kostenlose Software Adobe Digital Editions (siehe E-Book Hilfe).
- Tablet/Smartphone (Android; iOS): Installieren Sie bereits vor dem Download die kostenlose App Adobe Digital Editions oder die App PocketBook (siehe E-Book Hilfe).
- E-Book-Reader: Bookeen, Kobo, Pocketbook, Sony, Tolino u.v.a.m. (nicht Kindle)
Das Dateiformat PDF zeigt auf jeder Hardware eine Buchseite stets identisch an. Daher ist eine PDF auch für ein komplexes Layout geeignet, wie es bei Lehr- und Fachbüchern verwendet wird (Bilder, Tabellen, Spalten, Fußnoten). Bei kleinen Displays von E-Readern oder Smartphones sind PDF leider eher nervig, weil zu viel Scrollen notwendig ist.
Mit Adobe-DRM wird hier ein „harter” Kopierschutz verwendet. Wenn die notwendigen Voraussetzungen nicht vorliegen, können Sie das E-Book leider nicht öffnen. Daher müssen Sie bereits vor dem Download Ihre Lese-Hardware vorbereiten.
Bitte beachten Sie: Wir empfehlen Ihnen unbedingt nach Installation der Lese-Software diese mit Ihrer persönlichen Adobe-ID zu autorisieren!
Weitere Informationen finden Sie in unserer E-Book Hilfe.