
Practical Guide to the NEC3 Engineering and Construction Contract
Description
Alles über E-Books | Antworten auf Fragen rund um E-Books, Kopierschutz und Dateiformate finden Sie in unserem Info- & Hilfebereich.
More details
Other editions
Additional editions


Person
Content
1.1 General 1
1.2 Mechanics not law 2
1.3 A simple formula for understanding a contract 3
1.4 Mandatory or discretionary 4
1.5 Conditions precedent 4
1.6 Note on use of upper case in key words and phrases 5
2 Background to the NECECC 7
2.1 The background: First edition 7
2.2 The second edition 8
2.3 The third edition 9
2.4 The third edition (re?]printed) 9
2.5 Endorsement of NEC3 by the Office of Government Commerce 10
2.6 General philosophy: Aims and objectives 11
2.7 Flexibility 11
2.8 Clarity and simplicity 11
2.9 Stimulus to good management 12
2.10 Other characteristics 13
3 The Options: An Overview 15
3.1 General arrangement of the ECC 15
3.2 Other documents referred to 17
3.3 Contract Data 18
3.4 The published documents 18
3.5 Main Options: General outline 19
4 'Spirit of Mutual Trust and Cooperation' 23
4.1 Introduction 23
4.2 Core clause 10.1 23
4.3 What does it mean? 25
4.4 Practical issues 26
5 The Cast of Characters 29
5.1 Introduction 29
5.2 The Employer 29
5.3 The Project Manager 31
5.4 The Supervisor 33
5.5 The Contractor 34
5.6 The Adjudicator 35
5.7 Subcontractors 36
5.8 'Others' 36
5.9 Named Suppliers 37
5.10 Designers 37
5.11 Principal Designer 38
5.12 Principal Contractor 39
5.13 Practical issues 39
6 Communications, Early Warnings and other General Matters 41
6.1 Introduction 41
6.2 Communications: The clause 41
6.3 Communications: Practical issues 42
6.4 Early warnings: The clause 45
6.5 Early warnings: Practical issues 46
6.6 Other matters: The clauses 49
6.7 Other matters: Practical issues 52
7 The Contractor's Main Responsibilities 55
7.1 Introduction 55
7.2 Providing the Works 55
7.3 Contractor's design 57
7.4 Other matters 58
7.5 Practical issues 61
8 Subcontracting 65
8.1 Introduction 65
8.2 Definition of a Subcontractor 65
8.3 The core clauses 66
8.4 Provisions in the Main Options 67
8.5 Practical issues 67
8.6 Options for forms of subcontract in the NEC3 family 68
9 Testing and Defects 71
9.1 Introduction 71
9.2 Tests and inspections 71
9.3 What is a Defect? 73
9.4 The Defect procedure 73
9.5 The Defects Certificate 75
9.6 Uncorrected Defects 76
9.7 Practical issues 77
10 Title 81
10.1 Introduction 81
10.2 The core clauses 81
10.3 Practical issues 82
11 Risks and Insurance 85
11.1 Introduction 85
11.2 The core clauses 85
11.3 Practical issues 88
12 Time 91
12.1 Introduction 91
12.2 The programme: Contents 92
12.3 The programme: Submitting, accepting and revising 97
12.4 The programme: Practical issues 99
12.5 Starting and finishing 108
12.6 Other matters 111
12.7 Secondary Options related to Time 114
12.8 Practical issues 117
13 Payment 121
13.1 Introduction 121
13.2 The payment process 121
13.3 Payments in multiple currencies 124
13.4 The amount due and the PWDD 124
13.5 Supporting documents and records 134
13.6 The Contractor's share 138
13.7 The Contractor's share: Practical issues 139
13.8 Special provisions for the UK 141
13.9 Related Secondary Options 143
13.10 Practical issues 148
14 The Schedules of Cost Components 153
14.1 Introduction 153
14.2 The Schedule of Cost Components 153
14.3 The Shorter Schedule of Cost Components 158
14.4 Application to Subcontractors 159
14.5 Practical issues 160
15 Compensation Events: Theory and Events 165
15.1 Introduction 165
15.2 The theory 165
15.3 The events 167
15.4 Practical issues 182
16 Compensation Events: Procedures 187
16.1 Introduction 187
16.2 Notification by the Project Manager 189
16.3 Notification by the Contractor and the Project Manager's reply 192
16.4 Other matters associated with notifying compensation events 195
16.5 Quotations: Substance 197
16.6 Quotations: Submission and reply 199
16.7 Assessments by the Project Manager 204
16.8 Implementing compensation events 206
16.9 Practical issues 207
17 Compensation Events: Assessment 215
17.1 Introduction 215
17.2 Changes to the Prices 216
17.3 Changes to the Completion Date and any Key Dates 220
17.4 Project Manager's assumptions 223
17.5 Other related matters 224
17.6 Practical issues 226
18 Termination 229
18.1 Introduction 229
18.2 Reasons for termination 229
18.3 Implementing termination 233
18.4 Procedures after termination 234
18.5 Assessing the amount due after termination 235
18.6 Practical issues 237
19 Dispute Resolution 239
19.1 Introduction 239
19.2 Option W1 240
19.3 Option W2 243
19.4 Practical issues 248
20 Secondary Options 251
20.1 Introduction 251
20.2 X2: Changes in the law 251
20.3 X4: Parent company guarantee 252
20.4 X12: Partnering 252
20.5 X13: Performance bond 257
20.6 X17: Low performance damages 258
20.7 X18: Limitation of liability 258
20.8 X20: Key Performance Indicators 259
20.9 Y(UK)3: The Contracts (Rights of Third Parties) Act 1999 260
20.10 Z: Additional conditions of contract 260
20.11 Practical issues 262
21 Completing the Contract Data 263
21.1 Introduction 263
21.2 Purpose and form of the Contract Data 263
21.3 Part One: Data for the core clauses 264
21.4 Part One: Data for the Main Option clauses 268
21.5 Part One: Data for the Secondary Option clauses 269
21.6 Part Two: Data for the core clauses 273
21.7 Part Two: Data for the optional statements 274
21.8 Part Two: Data for Main Option A or B 275
21.9 Part Two: Data for Main Option C, D or E 276
21.10 Practical issues 278
22 The Supporting Documents: Need and Content 283
22.1 Introduction 283
22.2 Works Information 283
22.3 Site Information 293
22.4 Practical issues 294
Bibliography 297
Appendix 1 Tables of Clause Numbers, Case Law and Statutes 299
Appendix 2 Tables of Employer's, Project Manager's, Supervisor's, Contractor's and Adjudicator's Actions 309
Appendix 3 Tables of Communication Forms and Their Uses 337
Chapter 1
Introduction
1.1 General
In writing this guide I have set out to provide a view, much of it personal, as to how to get the most out of the third edition of the New Engineering Contract Engineering and Construction Contract (ECC). It is no secret that I am a fan of this contract and, as a result, may be willing to overlook what many perceive as it faults or weaknesses. In this guide I have tried to identify and suggest ways in which the procedures and aims of the contract can be simplified so that users do not become unnecessarily bogged down in procedure, but instead concentrate on achieving the goals of the ECC. This guide therefore goes through the procedure in detail as intended by the relevant clauses, but concentrates on practical issues to provide suggestions which the parties can use to achieve the overall intent and spirit of the ECC and to reach the common goal.
With this guide, you get what it says on the cover: A Practical Guide to the NEC3 ECC Form of Contract. It is a guide to provide users of the ECC, both novice and experienced, with a view of all its various philosophies, principles, mechanisms and vagaries. The reader will be guided through the contract in a manner that will enable him or her to use this guide for reference without necessarily having to read it all: in other words, a practical guide rather than a stuffy text book. That said, there will be an amount of cross-referencing between sections in order to avoid repetition, so users will need to follow these references to find more detailed supporting guidance to particular issues. One area that is not cross-referenced is the term 'spirit of mutual trust and cooperation' as found in clause 10.1 of the ECC, although used extensively throughout the guide. If users are uncertain of the meaning of this phrase, then they need to re-read Chapter 4.
To assist the reader in finding where any particular clause, related legal case or UK statute is referred to in the text, a comprehensive index of such references is included in Tables A1.1-A1.3 in Appendix 1.
The more I have worked with this contract over the years, the more I have come to think of it not as a contract but as a Project Management Procedures Manual. This should not be a surprise as the original contract was drafted by project managers for construction professionals (and not by lawyers for other lawyers and judges).
Nevertheless, we must not lose sight of the fact that the ECC is a contract and, as such, legally binds those parties that enter into a contract incorporating these standard terms.
This second edition of the book was requested by the publisher after three successful years for the first edition. During that period, NEC had re-printed the third edition of the contract, together with the rest of the family. This re-print had made relatively minor amendments to a number of clauses and introduced a new secondary option for use in the UK. These amendments have been incorporated into the text as part of this revision. At the same time, references to the previous text have been expunged. The clauses that have been amended as part of the re-print are indicated in Table A1.1 of Appendix 1 by means of an asterisk (*) in the clause number column.
In addition, NEC had issued amendments in September 2011 which made changes to two of the Options (W2 and Y(UK)2) to cater for the amendments to the Housing Grants, Construction and Regeneration Act 1996 contained in the Local Democracy, Economic Development and Construction Act 2009, which became effective for all new contracts entered into from 1 October 2011. These had been referred to in the first edition of this book as being expected to be effective from 1 April 2011, but the delay had not been announced until the original text had gone to print.
Within this revision I have also taken the opportunity to make amendments and additions to the contents to include my own evolving knowledge of the ECC and developments to the practical side which have come to my attention from various sources. Some useful suggestions from reviewers of the first edition commissioned by the publisher have also been considered and included as appropriate and practical.
1.2 Mechanics not law
Being a practical guide, this book considers the mechanics of the contract and not of the law. As a practicing construction professional, I am interested in the successful outcome of the project for all parties involved. From my point of view, the employing organisation should get what it wants in terms of a project finished on time, to the required quality and within budget (providing, of course, that the budget was reasonable in the first place). The consultants should be recognised for their contribution, whether it be design, management or commercially orientated, and be paid a reasonable fee for the service they provide. The contractors and subcontractors who carry out the work should be allowed to work efficiently, be recognised as having contributed to the project and make a profit.
Only those projects that satisfy all of the above criteria should be considered as being successful. Every organisation, whether it be a company, partnership or individual who is involved in a project, has its own needs and goals from that project. A good project will recognise this simple fact of business. It is when all the parties involved recognise each other's business goals (see Section 4.4.3) from the project, and work to align these goals, that success is achieved for all. As soon as one of the organisations involved feels dissatisfied, then the seeds of a dispute have been sown. As the industry knows, such seeds germinate easily and freely; once they appear on a project they can spread faster than any invasive weed.
Following on from the earlier editions, the ECC is drafted to impose the best practices within project management on the parties with the goal of avoiding disputes. It is the mechanics of these procedures and how to make them work effectively that is the focus of this guide.
As a consequence the guide does not consider the law in relation to the ECC, except where reference is needed to explain why something is included or to confirm that, in relation to the law in the UK, those requirements have been complied with by the ECC (or not as the case may be).
1.3 A simple formula for understanding a contract
Let us face it: all contracts are confusing when you first try to work out what it all means. I picked up a simple formula for considering contracts many years ago from an experienced Chief Quantity Surveyor of a contracting organisation, who came to my then local centre of The Chartered Institute of Building to give an evening talk on Joint Contracts Tribunal (JCT) Contracts. It did not matter that he was talking about JCT Contracts. What I took away from that talk was a formula which I still use today in relation to any contract or procedural document that I encounter; this formula holds good in all such situations. I still have the piece of paper on which I noted the few words I needed to remind me of what to do. I rarely look at that piece of paper now as the formula has become second nature to me in relation to every contract or set of procedures which I read.
The formula is in two parts. The first part can be remembered by four words: WHO, WHAT, WHEN and HOW.
To expand, a contract is a document which sets out the rights and obligations of the parties to that contract, no matter what the contract is for. In the construction and related industries such contracts cover (usually by necessity) a range of extensive rights and obligations for both parties, how such rights and obligations are to be administered and the involvement of agents to carry out specified duties for one or both of the parties. WHO, the first of our four key words, relates to the administration of these rights and obligations. The WHO in the ECC will be one of the five named persons including the Employer, the Project Manager, the Supervisor, the Contractor or the Adjudicator. The specific roles of these individuals are covered in detail in Sections 5.2-5.6.
By its processes and procedures, the ECC sets out WHAT must or may be done in the event that a certain circumstance arises. The WHAT will involve the WHO doing something as set out in the contract.
WHEN that something is to be done is also set out by the contract. In the case of the ECC, the timetable for WHEN these things shall be done is clear and forms a key part of the processes and procedures under the contract. Failure to comply with these processes and procedures in accordance with the requirements specified by WHEN can result in a right being forfeited because of this failure.
Finally, the ECC sets out HOW the process or procedure shall be carried out. Again, the ECC is prescriptive as to the HOW, although much of the HOW is set out in general terms that apply across all of the subsequent detailed processes and procedures.
To summarise, the first part of the formula (which holds good for all contracts and not just the ECC) is to consider WHO does WHAT, WHEN they do it and HOW it is to be done. Understanding these things is important as the ECC creates what are known in legal circles as conditions precedent. Although the English Courts do not like such provisions, they can be effective if drafted in certain terms (for further comment on conditions precedent, see Section 1.5).
When dealing with specific processes and procedures in this guide,...
System requirements
File format: ePUB
Copy protection: Adobe-DRM (Digital Rights Management)
System requirements:
- Computer (Windows; MacOS X; Linux): Install the free reader Adobe Digital Editions prior to download (see eBook Help).
- Tablet/smartphone (Android; iOS): Install the free app Adobe Digital Editions or the app PocketBook before downloading (see eBook Help).
- E-reader: Bookeen, Kobo, Pocketbook, Sony, Tolino and many more (not Kindle).
The file format ePub works well for novels and non-fiction books – i.e., „flowing” text without complex layout. On an e-reader or smartphone, line and page breaks automatically adjust to fit the small displays.
This eBook uses Adobe-DRM, a „hard” copy protection. If the necessary requirements are not met, unfortunately you will not be able to open the eBook. You will therefore need to prepare your reading hardware before downloading.
Please note: We strongly recommend that you authorise using your personal Adobe ID after installation of any reading software.
For more information, see our ebook Help page.