
Building Contract Claims
Description
Alles über E-Books | Antworten auf Fragen rund um E-Books, Kopierschutz und Dateiformate finden Sie in unserem Info- & Hilfebereich.
More details
Other editions
New editions

Additional editions


Person
Content
Acknowledgements x
Contract abbreviations xi
PART I 1
1 Introduction 3
1.1 Structure of the book 3
1.2 Types of claims 3
1.3 The basis of claims 8
1.4 Architect's and contract administrator's powers and liability to contractor 11
1.5 Quantity surveyor's powers 16
2 Time 20
2.1 Time of the essence 20
2.2 Time at large 22
2.3 Extension of time clauses in contracts 26
2.4 Concurrency 32
2.5 Acceleration 40
2.6 Sectional completion 47
2.7 The SCL extension of time Protocol 51
3 Liquidated damages 57
3.1 The meaning and purpose of liquidated damages 57
3.2 Liquidated damages or penalty 58
3.3 Liquidated damages as limitation of liability 65
3.4 Sums greater than a genuine pre-estimate 66
3.5 Liquidated damages as an exhaustive remedy 67
3.6 Injunction 72
3.7 Liquidated damages in relation to loss 74
3.8 Where there is no breach of contract 75
3.9 Calculation of liquidated damages 77
3.10 Where there is partial possession 78
3.11 Maximum recovery if sum is a penalty 80
3.12 Maximum recovery if liquidated damages do not apply 82
3.13 Defences to liquidated damages in building contracts 84
3.14 Bonus clauses 93
4 Basis for common law claims 95
4.1 General 95
4.2 Implied terms 97
4.3 Variation of contract 103
4.4 Omission of work to give it to others 104
4.5 Extra work 107
4.6 Possession of site 109
4.7 Site conditions 113
5 Direct loss and/or expense 117
5.1 Defi nition 117
5.2 Direct v indirect 118
5.3 Exclusion of consequential loss 120
6 Points of principle 123
6.1 Measure of damages 123
6.2 Burden of proof 124
6.3 Res ipsa loquitur 125
6.4 Mitigation of loss 125
6.5 Betterment 127
6.6 Notices 128
6.7 Categories of claim 135
7 Potential heads of claim 140
7.1 Foreshortened programme 140
7.2 The 'knock-on' effect 143
7.3 The more common heads of loss 147
7.4 Cost of a claim 180
8 Causation 182
8.1 Theory 182
8.2 Use of networks 184
8.3 Float 189
9 Global claims 192
9.1 Basic principles of global claims 192
9.2 Unacceptable global claims 194
9.3 The current position 196
10 Preparation and substantiation of claims 201
10.1 Preparing a claim 201
10.2 Types of evidence required to support a claim 206
10.3 'Scott schedules' 213
PART II 217
11 Extension of time under JCT standard form contracts 219
11.1 Standard Building Contract (SBC) 219
11.2 Intermediate Building Contract (IC and ICD) 248
11.3 Minor Works Building Contract (MW and MWD) 251
11.4 Design and Build Contract (DB) 254
11.5 Prime Cost Building Contract (PCC) 256
11.6 Management Building Contract (MC) 257
11.7 Construction Management Trade Contract (CM/TC) 259
11.8 Major Project Construction Contract (MP) 260
11.9 Measured Term Contract (MTC) 262
11.10 Constructing Excellence Contract (CE) 264
12 Liquidated damages under JCT standard form contracts 268
12.1 Standard Building Contract (SBC) 268
12.2 Intermediate Building Contract (IC and ICD) 273
12.3 Minor Works Building Contract (MW and MWD) 273
12.4 Design and Build Contract (DB) 274
12.5 Prime Cost Building Contract (PCC) 275
12.6 Management Building Contract (MC) 275
12.7 Construction Management Trade Contract (CM/TC) 275
12.8 Major Project Construction Contract (MP) 276
12.9 Measured Term Contract (MTC) 276
12.10 Constructing Excellence Contract (CE) 277
13 Loss and/or expense under JCT standard form contracts 278
13.1 Standard Building Contract (SBC) 278
13.2 Intermediate Building Contract (IC and ICD) 305
13.3 Minor Works Building Contract (MW and MWD) 309
13.4 Design and Build Contract (DB) 311
13.5 Prime Cost Building Contract (PCC) 315
13.6 Management Building Contract (MC) 316
13.7 Construction Management Trade Contract (CM/TC) 316
13.8 Major Project Construction Contract (MP) 316
13.9 Measured Term Contract (MTC) 318
13.10 Constructing Excellence Contract (CE) 318
14 Variations 319
14.1 Introduction 319
14.2 The baseline 320
14.3 Bills of quantities 321
14.4 Functions of the architect and the quantity surveyor 324
14.5 JCT Standard Building Contract (SBC) 325
14.6 JCT Intermediate Building Contract (IC and ICD) 345
14.7 JCT Minor Works Building Contract (MW and MWD) 350
14.8 JCT Design and Build Contract (DB) 352
14.9 JCT Prime Cost Building Contract (PCC) 360
14.10 JCT Management Building Contract (MC) 361
14.11 JCT Construction Management Trade Contract (CM/TC) 361
14.12 JCT Major Project Construction Contract (MP) 362
14.13 JCT Measured Term Contract (MTC) 364
14.14 JCT Constructing Excellence Contract (CE) 366
PART III 367
15 Claims Under The General Conditions of Government Contracts for Building and Civil Engineering Works (GC/Works/1(1998)) 369
15.1 Introduction 369
15.2 Extension of time and liquidated damages 369
15.3 Prolongation and disruption 377
15.4 Valuation of instructions 381
16 Claims under the ACA Form of Building Agreement (ACA 3) 385
16.1 Introduction 385
16.2 Extension of time and liquidated damages 386
16.3 Prolongation and disruption 395
16.4 Valuation of instructions 402
17 Claims under the ACA Standard Form of Contract for Project Partnering (PPC2000) 407
17.1 Introduction 407
17.2 Extension of time and damages 408
17.3 Loss and/or expense 413
17.4 Changes 415
18 Claims under NEC 3 Engineering and Construction Contract (NEC 3) 418
18.1 Introduction 418
18.2 Compensation events 420
18.3 Delay damages 444
19 Sub-contract claims 446
19.1 Introduction 446
19.2 JCT Standard Building Sub-Contract Conditions (SBCSub/C) 446
19.3 JCT Standard Building Sub-Contract with Sub-Contractor's Design Conditions (SBCSub/D/C) 457
19.4 JCT Intermediate Named Sub-Contract Conditions (ICSubNAM/SC) 458
19.5 JCT Intermediate Sub-Contract Conditions (ICSub/C) 459
19.6 JCT Intermediate Sub-Contract with Sub-Contractor's Design Conditions (ICSub/D/C) 460
19.7 JCT Design and Build Sub-Contract Conditions (DBSub/C) 460
19.8 JCT Management Works Contract Conditions (MCWC/C) 462
19.9 ACA Form of Sub-Contract (ACA/SC) 465
APPENDIX 473
Example of contractor's claim for reimbursement of direct loss and/or expense under SBC with quantities clauses 4.23-4.26 - architect's and quantity surveyor's assessment with commentary 475
Table of cases 498
Table of standard form contract clauses 512
Index 523
PART I
Chapter 1
Introduction
1.1 Structure of the Book
The book has been arranged in three parts:
Part 1 deals with general principles relating to time, liquidated damages and financial claims of various kinds.
Part 2 looks at the relevant clauses in JCT contracts.
Part 3 looks at the equivalent clauses in other standard contracts and in some standard sub-contracts.
1.2 Types of Claims
The dictionary defines ‘claim’ as ‘a demand for something as due’.1 Standard form contracts do not use the word ‘claim’. In this book the word is taken to mean the assertion of an alleged right, usually by the contractor, to an extension of the contract period and/or to payment arising under the express or implied terms of a building contract. In the construction industry a ‘claim’ is usually used to describe any application by the contractor for payment which is additional to the payment to which it would be entitled under the general interim payment provisions in the building contract. Although commonly associated with money (i.e. a claim for direct loss and/or expense) ‘claim’ is also used to describe a contractor’s application for extension of time. If it was not for ‘claims clauses’ in building contracts, the contractor would be obliged to fall back on a common law claim for damages (usually for breach of contract). In that sense, claims clauses may be considered, albeit not entirely correctly, as a contractual procedure for dealing with damages. More will be said about this later in the book.
It is useful to classify claims by contractors against employers into four categories. They are: contractual claims, common law claims, quantum meruit claims and ex gratia claims. It should not be forgotten that an employer may make claims against a contractor for liquidated damages or for payment of a balance owing on the final certificate or after termination of the contractor’s employment by the employer.
1.2.1 Contractual Claims
These are claims which are based on a clause or clauses in the contract which expressly provide for the contractor to make a claim in certain prescribed situations. A prime example is the direct loss and/or expense clause 4.23 in the Joint Contracts Tribunal Limited (JCT) Standard Building Contract 2005 (SBC). Such claims make use of the machinery in the contract to process the claim and produce a result. The principal reason for having such provisions in the contract is to avoid the necessity for the contractor to have to seek redress at common law and the inevitable expense involved for both parties in doing so. Most standard form contracts in any event preserve the contractor’s right to seek damages at common law if it is not satisfied with its reimbursement under the contract.
1.2.2 Common Law Claims
Common law claims are claims for damages, usually but not exclusively, for breach of contract under common law. They may also embrace claims for breach of some other aspect of the law such as tortious claims or claims for breach of statutory duty. Most standard forms expressly reserve the contractor’s right to make such claims, for example SBC clause 4.26. A common law claim may be made when it is impossible or difficult to make the claim under the contractual machinery, perhaps because the contractor has failed to comply with the criteria set out in the contract within the appropriate timescale. The making of an application within a reasonable time is an example of such a criterion. However, a common law claim may be more restricted in scope than the matters for which a contractual claim can be made, some of which (for example, architects’ instructions) are not breaches of contract. Common law claims are sometimes referred to as ‘ex-contractual’ or ‘extra-contractual’ claims. These terms are sometimes confused with the term ex contractu. That term is, rarely, found in certain legal textbooks when referring to claims which arise from the contract.
1.2.3 Quantum Meruit Claims
A quantum meruit claim (‘as much as he has earned’) provides a remedy where no price has been agreed. There are four relevant situations:
(1) Where work has been carried out under a contract, but no price has been agreed.
(2) Where work has been carried out under a contract believed to be valid, but actually void.
(3) Where there is an agreement to pay a reasonable sum.
(4) Where work is carried out in response to a request by a party, but without a contract. This is usually termed a claim in quasi-contract or restitution. Work done following a letter of intent is a good example.
The type of claim and the method of valuation are two different things. It is useful to consider the method of valuation under two heads:
(1) Where there is a contract
(2) Where there is no contract.
Where There Is a Contract
For example a contractor may be instructed to carry out certain work to a property, but neither party has thought to agree the price before the work is commenced. In practice, this scenario is remarkably common. If the parties cannot subsequently agree the amount to be paid, the law is that the contractor would be entitled to a reasonable sum. In Turriff Construction v Regalia Knitting Mills2 a contractor tendered for a design and build contract. The employer was anxious for completion by an early date and much preparatory work had to be completed. Although many things, including the price, remained to be agreed, a letter of intent was issued. It was held that in the circumstances an ancillary contract had been entered into which entitled the contractor to payment on a quantum meruit basis.
In Amantilla Ltd v Telefusion PLC,3 the court had to decide whether a cause of action was resuscitated under the Limitation Act (1980), but the cause of action centred on a quantum meruit claim. The contractor had carried out work for the employer for an agreed lump sum price. It was agreed that the contractor should carry out substantial additional work, but the price was not agreed. Various payments were made by the employer, but a final offer by the employer was turned down and matters proceeded to the court which held that the contractor was held entitled to recover, because:
‘A quantum meruit claim for a “reasonable sum” lies in debt because it is for money due under a contract. It is a liquidated pecuniary claim because “a reasonable sum” (or a “reasonable price” or “reasonable remuneration”) is a sufficiently certain contractual description for its amount to be ascertainable in the way I have mentioned.’4
A contractor will often argue that it is entitled to recover on the basis of a complete re-rating of the bills of quantities or on a quantum meruit basis, because the whole scope and character of the work has changed. Most such claims are doomed to failure, because the Works as defined in the contract rarely change and all standard form contracts provide for instructions to be issued to add to, omit from and to vary the Works. The extent to which the Works can be varied without changing their essential character is an interesting topic.
A successful case involved a contractor which contracted to construct an ordnance factory for the employer.5 The contract sum was £3.5 million and there was a subsequent agreement that the employer would pay the cost of the Works plus profit of between £150,000 and £300,000. The contractor thought that the work would cost about £5 million. The value of the contract was eventually increased to £6.83 million. This amount was paid together with a further £300,000 as profit. However, the contractor contended that it was entitled to further profit, while the employer’s position was that it was entitled to order unlimited extras provided that the total Works remained within the scope of the project. In holding that the contractor was due to further reasonable remuneration calculated on a quantum meruit basis, the Court of Appeal stated that the contractor had believed that the cost of the Works would not exceed £5 million and, therefore, a term would be implied into the contract that the employer was not entitled to receive work materially in excess of £5 million. The Court’s view was that neither party could have contemplated such a great increase in the value of the work when the agreement was made.
Where There Is No Contract
In British Steel Corporation v Cleveland Bridge & Engineering Co Ltd,6 the employer had invited tenders for the fabrication of steelwork. The contractor was asked for cast steel nodes. Following the tender, a letter of intent was sent and, expecting a formal order, the contractor began work. Negotiations continued until almost the whole of the nodes had been manufactured and delivered. The court held that no contract had come into existence, the work had been carried out on the basis of the letter of intent and the contractor was entitled to be paid on a quantum meruit basis.
In another case7 a contractor submitted a tender for the design and construction of a factory. The contractor was informed that if certain insurance monies became available, its tender would be accepted. Before any such monies were available, the contractor was requested to, and did, carry out some design work...
System requirements
File format: ePUB
Copy protection: Adobe-DRM (Digital Rights Management)
System requirements:
- Computer (Windows; MacOS X; Linux): Install the free reader Adobe Digital Editions prior to download (see eBook Help).
- Tablet/smartphone (Android; iOS): Install the free app Adobe Digital Editions or the app PocketBook before downloading (see eBook Help).
- E-reader: Bookeen, Kobo, Pocketbook, Sony, Tolino and many more (not Kindle).
The file format ePub works well for novels and non-fiction books – i.e., „flowing” text without complex layout. On an e-reader or smartphone, line and page breaks automatically adjust to fit the small displays.
This eBook uses Adobe-DRM, a „hard” copy protection. If the necessary requirements are not met, unfortunately you will not be able to open the eBook. You will therefore need to prepare your reading hardware before downloading.
Please note: We strongly recommend that you authorise using your personal Adobe ID after installation of any reading software.
For more information, see our ebook Help page.